Team Safety Forms

Complete the appropriate hazard assessment before every job. COR certification requires all three forms to be used consistently — no exceptions on site.

COR CERTIFIEDSince 2015 — Landscape Alberta
Edmonton, AB Complete all required forms before starting work
Daily order:
1Site Specific (new site)
2Formal Hazard (task level)
3Tailgate Meeting (every morning)
1
Task Level — Foreman / Crew

Formal / Task Hazard Assessment

When to complete this form
  • Before starting work on specific tasks at the foreman or crew level
  • When new tasks are introduced on site that weren't part of the original scope
  • If there is a significant change in conditions, scope, or hazard exposure
  • When conflicting work arises between trades on site
  • Review with employees during tailgate meetings and post at workstations if applicable
Open Formal Hazard Assessment
2
Management / Supervisor — New Site

Site Specific Assessment / Pre-Job Hazard Assessment

When to complete this form
  • Before starting work on any new project or site — completed by management or supervisors
  • Must be done prior to any on-site activities — this is a pre-work planning document
  • Re-assess if there is a significant change in scope, conditions, or site hazards
  • Part of the COR-required planning process for every new job
Open Site Specific Assessment
3
Every Day Before Work Begins

Tailgate Meeting Daily

When to complete this form
  • Every single day, prior to starting work on site — no exceptions
  • Cover the day's tasks, identified hazards, controls in place, and emergency procedures
  • All crew members present must sign off — this is a COR requirement
  • Takes 5–10 minutes — do it before tools come off the truck
Open Tailgate Meeting Form

Emergency Contacts

Know these numbers before you start every shift.

Emergency Services

911
Police · Fire · Ambulance

Ryan Pon — Owner

(780) 709-0358
Call for any site incident

Alberta Poison Control

1-800-332-1414
Hazardous substance exposure